[Suspended ceiling PVC board installation]How to install PVC suspended ceiling installation steps
PVC suspended ceiling mainly refers to PVC gusseted ceiling, which is the modern ceiling market A type of ceiling decoration material that is often used in China is very suitable for the installation of kitchen and bathroom ceilings because of its light weight, moisture-proof, flame-retardant and easy to clean. There are naturally some different details in the process, and the matters needing attention in the installation process are also different from the installation of other materials. Let’s take a look at the installation of PVC ceiling!
PVC ceiling installation steps:
1. Determine the size:
The main thing is to make sure the size of the ceiling you need to install before installing the ceiling. If you can’t measure it yourself, you should ask a professional to do the measurement, but don’t underestimate the size measurement, this step is in the PVC gusset plate The ceiling installation process plays a vital role, because the material selection and installation in the future must be based on this size. If the size is incorrect, it will not only increase the installation cost, but also delay the construction period.
2. Install the edge trim:
Install the edge trim according to the same horizontal height. Steel keel (38 or 50 keel), the general spacing is 1-1.2 meters, and the distance of the boom is distributed according to the regulations of the light steel keel.
3. Installation of PVC gusset keel:
The installation work in this step is mainly to hang the pre-installed parts on the PVC gusset keel, together with the PVC buckle The plate keel is close to the light steel keel and is fastened under the light steel keel in a vertical direction with the light steel keel. The spacing between the PVC gusset keels is generally 1 meter, and the level must be adjusted after all installations are completed, so as to ensure that the entire gusset ceiling is neat after installation. smooth.
4. Install the PVC gussets:
Fasten the PVC gussets in parallel on the matching keel in order, when the PVC gussets are connected Connect with special keel series connectors. Gloves must be worn when installing the board. If fingerprints or stains are accidentally left, it can be washed with detergent and boiled water and then wiped dry. The good installation process is convenient for disassembly.
Precautions for the installation of PVC gusset ceiling:
Although the installation of PVC ceiling is really simple from the above installation steps, if the installation process is If you don’t pay attention to some details, then not only can’t guarantee the quality of its installation, let alone its aesthetics after installation, especially the installation of the ceiling above the kitchen or bathroom, you must know that the installation of the ceiling in these spaces also needs to involve Yuba or lamps and lanterns. Therefore, be careful during the installation process. It is recommended that you pay attention to the following major details during the installation of the PVC ceiling.
1. After the wall tiles of the kitchen and bathroom are pasted, the gusset manufacturer’s personnel can be notified to come and measure, which is mainly to save the construction period of the entire home improvement.
2. After the electric water heater and gas water heater are installed in place, the power lines for lighting and exhaust should be reserved to ensure the safety of home life in the future.
3. Before installing the ceiling, buy a Yuba, exhaust fan, range hood, etc., and get it to the site. The location of the opening of the range hood smoke pipe should be determined with the cabinet manufacturer.
4. The ceiling light should also be purchased in advance and sent to the ceiling installation site.
5. Please confirm the installation position of all the above electrical appliances so that the installation workers can open the holes. It must be determined at one time, so as to avoid rework and prolong the entire home improvement construction period.
6. During the construction of professional ceiling installation masters, it is recommended that the owner can observe or check at the installation site to see if it is installed in place. If there is any inappropriateness, it needs to be pointed out to the installer immediately and corrected for installation.